Start Date:
End Date:
Created plan and sheet for the audit.
audit sheet completed for DS & ARI, team to catch up content in March.
sheet was shared with the teams, and reps are posting the Trello card links after requesting - Katie checking links and updating sheet daily.
sheet was updated and reps were reminded to finish creating Feb makeup requests. 7 more for DS and 11 for ARI left.
All requests have been made except 1 DS client - will follow up w/the rep on Monday.
all remaining requests have been made and project is complete.
Description
Due to a miscommunication about content requirements with the keyword audit, we are missing some content requests for Feb.
...