Summary

Migrate from Yext to Uberall.

Target release

Priority

Status
colourRed
titlehigh

Project status

Status
colourRed
titleoff trackComplete

Progress

Status
colourGreen
title90%100%

Brand

Status
colourGreen
titleDS
Status
colourGreen
titleARI
Status
colourRed
titletcs
Status
colourRed
titleND

Owner

Grant Gooch

Team

Status Note

17 Need to update documentation and Trello todo lists. Complete

Key Dates

  •   LV - Send over test migration data. Grant sending TCS
  •   Grant & Samar - Send per brand customer migration list. In progress.
  •   Train SEO team with materials from UB
  •   Review data in sandbox and fix any errors
  •   Import data to production
  •   Spot check data in the production environment
  •   Complete fulfillment documentation
  •   Katie to audit the Uberall account post migration to clean out un needed accounts
  •  Scope next steps.

Resources

Directory Listing Migration

Expected impact

Actual impact

...

Need to update documentation and Trello todo lists.