Task

Note

Status
colourGreen
titleDone

ALL

Intro Call

Status
colourGreen
titleDone

UB

Send WhiteLabel Requirements doc

Status
colourGreen
titleDone

LV

Export Yext Data

-

Status
colourGreen
titleDone

LV

Provided full export of Yext Data to product and Uberall team

No longer paring back data before migration. Provide reduced list of accounts to UB

Determined to be done post migration by Ops.

Status
colourGreen
titleDone

ALL

Migration planning

  • Review Go-Live Plan + Dates

  • GBP + FB Connect Plan

LV

Samar & Grant

Provide reduced Provided full export of Yext Data to UBproduct and Uberall team

2/13/23

UB

Convert Yext Data

2/13/23

LV

Samar

Return white label req doc

https://arinet-my.sharepoint.com/:x:/g/personal/samar_hatem_leadventure_com/EVHJE6sPdrZOpnGcPKMBjD0BWLpzi7hVcg99TzjqafvmVw?e=YFmMhD

2/14/23 - 2/17/23

UB

Set up dashboards (SP/CSP) + whitelabel

2/20/23 - 2/24/23

ALL

Platform Training w/ SEO Team

  • UB - Send Partner Academy for others

2/22/23

UB

Test yext import to sandbox

2/22/23

LV

Samar & Grant

Review and fix errors (LV)

2/27/23

UB

Import POI to Production

2/27/23

LV

Grant & Samar

Spot check data

2/27/23

ALL

User Assignment

2/28/23

LV

Release data from Yext

3/1/23

UB

Start Sync

3/1/23 - 3/10/23

ALL

Sales Training

  • New Acquisition

  • Upsell

  • OEM

3/1/23 - 3/10/23

LV

Grant

Existing Connections Sync (Manually connect GBP & FB)

Lance added row.

3/1/23 - 3/10/23

ALL

GBP + FB link share to connect

3/1/23 - 3/21/23

ALL

DigMS Dev Team API integration review

3/31/23

Katie

Audit Uberall account post migration

...