🏁 Milestones / Project Timeline
- Build customer migration list. Samar. In progress.
- Import dealer list. Uberall. 2 weeks.
- Connect GBP and FB Accounts(TCS & NetDriven, DS & ARI few)
- Complete inital GBP and FB account connection outreach.
Next Actions
Questions
Questions | Answer | Who | When | Where |
---|---|---|---|---|
| Samar (Lance to assist when/if needed) | Samar & Tory |
| Meeting: Uberall Migration Internal Discussion |
| ||||
|
Decisions
Decision: Decided to not cut additional locations past the first location and to migrate all of them.
...